Tender evaluation for selecting a competent contractor
by
Ruwan K Jayasinghe
In order to select the lowest, qualified, responsive evaluated bid out of the bids received the tender evaluation is being done.
Tender evaluation can be divided in to two stages
1. Bid examination and determination of responsiveness
2. Detailed Bid Evaluation
Important factors to be considered in tender evaluation
Bid examination and determination of responsiveness
The bid examination and determination of responsiveness is being done in order to find the eligibility of the bidders and the responsiveness of the bids received
Eligibility of the bidders
First of all in the bids should be examine in order to ascertain the bidder are comply with the requirements of the bid conditions, therefore in this process its find out the eligibility of the bidder to go ahead with the project, here following factors are being considered
1. Past experience
2. Financial Stability
3. Personal capabilities
4. Equipment capabilities
5. Arbitration /Litigation history
Here the bidder should be show evidence of their qualification in terms of the bid documents
In order to find the eligibility of the bidder the following factors can be carefully followed
The following factors can be considered for checking capability and experience of the bidder
Experience
1. Demonstrated ability to work within the environment of the department and its clients
2. Demonstrated understanding of legislative and administrative framework in the service area of the department
3. Previous experience or demonstrated ability to meet the service needs
4. Management philosophy as it relates to staffing, personnel management and training
5. Approach to the provision of the services
6. Approach to quality management – quality assurance certification
7. Philosophy and approach towards innovation in providing and/or managing the specific services
8. Financial capacity
The following factors can be considered for checking technical, capabilities and Quality of the bidder
Technical
1. Proposal meets service specification
2. Tenderer technically capable
3. Tenderer complies with relevant regulations
4. Tenderer’s personnel adequately qualified
5. Tenderer’s facilities appropriate
Capability
1. Proposal demonstrates understanding of the outsourcing objective
2. Tenderer’s experience and reputation in the industry
3. Tenderer’s track record as contractor
Quality
1. Use of best practice in the service approach
2. Feasible innovations offered
3. Arrangement to ensure good customer service
Post qualification process
Post qualifications are being considered in order to make sure that the lowest evaluated bid has been submitted by a responsible and trustworthy bidder
Determination of substantially responsive tenders
Substantially responsive bid is means the bid one which is tally with the conditions and specifications of the bid documents
Unsigned bids
To bind legally a bid documents should have been properly signed by the contractor if not the bid can be cancelled on the ground of the bid documents are not legally binding
Absence of incorrect bid security
Bid security is a fixed sum for the security of the bids and this should be submit not less than the amount specified
Incomplete bids
Incomplete bids can be rejected here incomplete bids as an example number of items are not quoted
Lack of supporting documents
The following documents must be submitted with the bid documents
Proof of reliability of the equipment offered
The other is to provide additional details on the technical aspect of the bid
Lack of these documents it is considered as the major deviation and the bid can be rejected
Minor deviation
Minor deviation would be one which either
Has no validity on the bid
Has no affect on the price, quality or delivery of the goods or services offered
Has no specified in the bid documents as grounds for rejection of the bid
The following are such deviations
Request for an amount of advance payment and other payment terms
Non compliance with some regulations
Proposed changes in construction period which is not critical
Changes in specified method of construction or execution in non critical nature
Omissions of minor works items included in the scope of works
Detail evaluations for bids
The purpose of bid detailed evaluation is to determine the lowest evaluated bid from the substantially responsive bids received, the lowest evaluated may necessarily not be the lowest quoted bid. In order to determine the lowest evaluated bid accurately and efficiently a systematic procedure can be arrange as follow
Check of arithmetic errors correct if any and confirm with bidder
Arithmetic errors
1. Where there is a discrepancy between the amounts in figures and in words the amount in words is govern and
2. Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by the quantity
i. the unit rate quoted will govern
ii. Unless there is an obviously gross misplacement of the decimal point of the unit rate in such case the line total as quoted will govern and the unit rate will be corrected
Pricing errors
Technical errors
There may be items billed in m2 but priced in linear meter rates or vice versa, an oblivious misunderstanding of a description may be noted, so a technical check should be made to correct those errors
Unrealistic errors
If unrealistic law or high rates quoted by a tenderer is found for critical or very important items he should be requested to prove the satisfaction of the consultant how he could perform the particular items within that rate
If the clarifications given are unacceptable and tenderer would fail in performing on those rates the bid may be rejected
Unbalanced Bids
Unit rate for those work elements to be performed early during contract performance can be priced relatively high, thus requiring higher payments to the contractor in the early phase of the contract period than justified by the value of the work performed
Bidders who have reasons to believe the quantities given in the bid documents for one or more work items are underestimated will quote unduly high price for these items since payments in unit price contracts are based on actual quantities of work performed they would attempted to obtain higher payments than justified by the value of work performed
Negotiations with tenders
While evaluating a tender if there is a need for negotiation with the bidder on issues which can improve with negotiation it should be proceeded as an example if there is a huge quantity error through negotiation it can be changed
Examine the priced BOQ
Before accepting a tender a QS has to examine
1. Mathematical check
2. Technical check/pricing error or patent errors
3. Ensure that the tenders has not made such a serious mistake that he would prefer to withdraw the tender as he may at any time before acceptance
4. If the selected bidder is not the lowest bid submit the reasons to select it